Pay less notice with a bare zero circled and a sticker asking which clock applies, for the check before booking the reduced sum.

How to Check a Pay Less Notice Under the Construction Act (HGCRA 1996)

Mark a pay less notice against the final date that applies, the sum, and a basis on the notice, before you book the reduced figure.

•9 min read•Article
💡

Key takeaway in 30 seconds

A pay less notice under the Housing Grants, Construction and Regeneration Act 1996 replaces the notified sum when it is in time, states a sum, and states a basis on its face. Section 111 allows zero. Count back from the final date that applies. If a sliding final date fails, the England and Wales Scheme can set 17 days from the due date. Mark timing, sum, basis, and service before you book the reduced figure or start a smash-and-grab.

Mark one pay less notice against the final date that applies, the sum due, and a basis you can follow from the notice, before you book that sum or start a smash-and-grab. A smash-and-grab is a claim for the notified sum, not a fresh valuation. Section 111 requires the notified sum by the final date unless a valid pay less notice replaces it. Seven days is only the fallback. If a sliding final date fails, 17 days can apply instead.

Disclaimer: Checkory provides AI support, not legal advice. Consult a qualified lawyer for binding decisions.

Why mark one pay less notice before you book the reduced sum?

Book the reduced figure only after the notice is in time, states a sum, and states a basis you can follow from the notice itself. Deerns [2026] EWHC 1509 (TCC) refused a 30-day final date that could slide while the due date stayed fixed. Davies & Davies records the claim as £910,501.71 plus VAT. The Scheme then set 17 days.

A commercial Net 30 is a different test. See the Net 30 payment-terms checklist.

Checklist counting back from the final date, with a 4 October due date, no notice by 9 October, and a 30-day slide that can fail.
Count back from the final date that applies

Does the Construction Act apply to this contract?

Stop if this agreement is not a construction contract, or if the England and Wales Scheme does not apply. Section 104 covers construction operations, arranging them, or labour, including related design or surveying work. A contract of employment falls outside it. Part 2 can apply in England, Wales, or Scotland.

Section 106 excludes a residential occupier: work on a dwelling that party occupies or intends to occupy. An office fit-out is not that work. A Scottish contract uses Scotland's Scheme, not paragraphs 8 and 10 of SI 1998/649.

Record the due date and who had to give the payment notice

Write the due date, who had to give the payment notice, and the five-day window. Keep it separate from the pay less notice. Section 110A requires the notice not later than five days after the due date, with the sum considered due and the basis. Zero is allowed. If the contract does not say this, the Scheme applies.

A missed payer notice does not decide the later pay less notice. Section 110B can postpone the final date by the length of the payee's delay, or treat an earlier payee notification as the default notice. Not every application becomes that default notice.

❌

Typical mistake

Test the pay less notice on its own sum and basis. Do not treat a missing or invalid payment notice as automatically fatal. In Laing O'Rourke [2026] EWHC 612 (TCC) a bare payment notice did not remove pay less deductions of £2,428,614.47.

Which final-date clock do you count back from?

Choose the final date before you count backwards. Parties may agree any period to that date, but that period has to stay fixed once the due date is known. Fenwick Elliott records the Deerns judge as requiring that fixed period. A clause that postpones the final date because the application was late fails section 110(1)(b). Earlier slippage does not rewrite the contract.

If the clause fails, Scheme paragraph 8 sets 17 days from the due date: 4 October 2026 becomes 21 October 2026, not 3 November 2026. BCLP identifies section 110B as the only Act route that lengthens that gap.

Count the agreed period back from that clock. Section 111(7) uses the five days the parties agreed. Scheme paragraph 10 supplies seven days only if the parties failed to agree. The Commercial Payments Bill is not in force: Gowling WLG, on 14 October 2026, records a Lords third reading due on 20 October 2026. Do not apply a seven-day minimum or a 30-day or 60-day cap.

Two final-date clocks, counted back five days

ClockFinal date from 4 October 2026Last day on a five-day periodWhat to write
Printed 30-day final date that can slide if the application is late3 November 202629 October 2026Deerns refused this slide. A 20 October email can look early here.
Scheme paragraph 8: 17 days from the due date21 October 202616 October 2026Deerns notices on 27 February and 25 March 2026 were late against 21 February and 23 March.
Two final-date clocks side by side, a printed 30-day date and a 17-day Scheme date, with 20 October between the last days.
The 20 October email falls between the last days

Can you follow the sum and the basis from the notice itself?

State the sum due on the date of the notice and the basis of that sum. Section 111(4) allows zero and still requires the basis. Stevens & Bolton records deductions of £2,428,614.47 from £5,627,275.11, leaving £3,198,660.64 plus VAT, because the build-up was on the pay less notice. Holmes & Hills says a bare figure fails unless the notice incorporates the schedule. A reasonable recipient must see the basis. "Valuation to follow" does not.

One document cannot do both jobs. Gowling WLG records Vision Construct Ltd v Gypcraft [2025] EWHC 2707 (TCC): a late payment notice cannot be relabelled as a pay less notice. Foot Anstey on Placefirst [2025] EWHC 100 (TCC) records a letter and a spreadsheet, sent 31 July 2024, as two notices.

Was the notice served the way the notices clause requires?

Mark method, address, and any attachment the notices clause requires, separately from the date. If email counts only when the notice is attached, a bare email fails service even if the dates would have worked. Do not invent a deemed-receipt rule. Deemed receipt is covered in the notices-clause review.

Log of the sum due, a basis on the face of the notice, an email with no attachment, and the fork before booking a bare zero.
Chase the notified sum or take advice

Chase the notified sum, accept the reduced sum, or take advice?

The log reaches a fork: chase the notified sum, accept the reduced sum, or take advice before a smash-and-grab. If the notice is in time and has a sum and a basis, section 111(6) makes that the sum payable. Surveyor Success describes Grove as paying the notified sum first, then a separate true-value adjudication.

If the notice is late, or it has no basis on its face, do not book a bare zero. A missing payment notice is not the reason the later notice fails. Section 108 provides for referral within 7 days and a decision within 28 days of referral, longer by agreement or by up to 14 days with the referring party's consent. That timetable is not the referral.

Where the choice is still 16 October or 29 October, take the log to a construction solicitor before you book either figure. Upload the subcontract and the email on document analysis.

Mark this October cycle before you book the email

1

Confirm the Act gateway

Subcontract of 12 March 2026, office fit-out in England, English law: construction contract, not a residential occupier. If the operations are in Scotland, stop. Do not use SI 1998/649.

2

Write the due date and the payment-notice window

Application 7 on 1 October 2026 claims £186,400. Due date 4 October 2026. No payment notice by 9 October 2026. Do not let that gap decide the pay less email.

3

Choose the final-date clock

Clause 7 states 30 days after the due date, postponed if the application is late. If paragraph 8 applies, write 21 October 2026, not 3 November 2026.

4

Count the agreed five days back

Five days before the final date: 16 October 2026 on the 21 October clock, or 29 October 2026 on the printed 30-day date. The 20 October email sits between them. Keep five days, not paragraph 10's seven.

5

Read the sum and the basis on the email

The 20 October email says £0 is due and a valuation will follow. Nothing is attached. Zero can be a sum. Those words are not a basis, and the application's schedule is not incorporated.

6

Mark service on the notices clause

To the commercial manager at a named postal address, or by email only if the notice is attached. This email has no attachment.

7

Stop on the fork

Chase the notified sum, accept the reduced sum, or take advice before a smash-and-grab. Do not book a bare zero.

Frequently asked questions

Does an invalid payment notice invalidate a later pay less notice?▼
No. Test the later notice on its own sum and basis. Laing O'Rourke kept deductions of £2,428,614.47 despite a bare payment notice.
Can one document be both a payment notice and a pay less notice?▼
No. A late payment notice cannot be relabelled. Two distinct documents in one email can still be two notices. Check each window.
What pay less deadline applies if the contract is silent?▼
Scheme paragraph 10 says seven days before the final date, and only if the parties did not agree a period. Keep an agreed five days.
Can a pay less notice say the sum due is zero?▼
Yes. Section 111(4) allows zero. The basis is still required on the face of the notice. "Valuation to follow" is not that basis.
Does the application automatically become the notified sum?▼
Not always. Section 110B may postpone the final date after a missed payer notice, or treat an earlier payee notice as the default. Read the clause first.
Can a true-value fight replace this checklist?▼
No. Pay the notified sum first, then a separate true-value adjudication can follow. Section 111(9) makes any further sum due on the later of seven days from the decision or the original final date.

Read the notice against the clock that applies

Upload the subcontract and the pay less email. Extract the final date, the agreed period, and the sum.

Review the notice

What to do next