
How to Review a Defects-Liability Period After Acceptance
Write the defects clock as Acceptance not invoice, keep a latent carve-out, refuse five-day silence as deemed Acceptance, then lengthen or walk.
Key takeaway in 30 seconds
Knowing how to review a defects-liability period after acceptance means writing the start as Acceptance or go-live, not first invoice, keeping a latent-defect and fraud carve-out so a hidden bug after day 30 stays their cost, and refusing five days of silence as deemed Acceptance. A spec-fail is their-cost, not a paid change order. Then lengthen, carve latent, or walk.
Della, Ops at a 22-person UK marketplace, is about to treat a thirty-day defects clock as stationery because Finance signed the build. Knowing how to review a defects-liability period after acceptance is a 25-minute hunt: write the start as Acceptance or go-live not invoice, keep a latent carve-out, refuse a change-order label on a spec-fail, and refuse five days of silence as deemed Acceptance. Then lengthen, carve latent, or walk.
September 2026. English law; exclusive courts of England and Wales. The PDF is an MSA — master services agreement, the vendor frame plus this SOW. Clause 9: “The defects liability period shall be thirty (30) days from Acceptance.” Clause 8: five (5) days of silence deems the Deliverable accepted. No latent-defect or fraud limb.
Last month a race condition appeared only under live seller load; the vendor ticketed it as “enhancement — change order.” AE Slack: “Thirty days is standard. You went live.” Friday is booked. The rush is the problem. The hidden risk is silence creating Acceptance.
A 12-month construction defects window is not a liability cut-off — and Della’s thirty days plus five-day silence is the inverse. JCT’s Making Good note: the name makes people think expiry ends liability; latent still survives making-good. Gebai (20 July 2026) sells UK new-build DLP as typically 12 months from practical completion — colour, not her SOW.
Disclaimer: Checkory provides AI support, not legal advice. Consult a qualified lawyer for binding decisions.

Which date starts the defects clock — acceptance or first invoice?
The defects clock starts on Acceptance, or on go-live if you redline that, not on first invoice. Circle “thirty (30) days from Acceptance.” If clause 8 already deems Acceptance after five days of silence, those thirty days may already be running. Write the trigger: Acceptance, go-live, delivery, or invoice.
David Tollen (updated 10 April 2023): he does not often see software warranties shorter than ninety days; thirty days seems to be the bottom. Custom work: the customer wants go-live. BuildAlliance: the clock starts on practical completion, not the first invoice. Do: write “trigger = Acceptance / go-live.” Don’t: let invoice eat the thirty days.

Typical mistake
Treating “thirty days from Acceptance” as stationery while five days of silence already is Acceptance. The clock can start in an inbox.
Della’s clauses 8 and 9
| Line | Della’s paper | Write |
|---|---|---|
| Start | Thirty (30) days from Acceptance | Acceptance / go-live / invoice |
| Length | 30 days | 30 vs 90 — vendor floor |
| Latent / fraud | None | Missing — fail |
| Their-cost vs CO | Live bug billed as change order | Spec-fail = their cost |
| Deemed | Five (5) days’ silence | Inbox / pause — fail |
What does a latent defect after the window still need — a carve-out?
After day 30, a bug a five-day staging click-through could not reasonably find still needs a limb: latent defects and fraud stay their cost. Della’s paper has none. Log “no carve-out — fail.”
JCT colour is the inverse: people think DLP expiry ends liability; it does not. Fenwick Elliott: a DLP is not, unless clearly stated, an exclusive remedy. Do not treat Limitation Act 1980 s.5 as six years of free fixes — that is when a claim may be brought. Do: demand a latent / fraud limb. Don’t: treat day 30 as a wipe.

Why does a spec-fail stay their cost, not a paid change order?
A Defect is a failure to meet the signed spec. A change order is new or different scope. Della’s live-load race was billed as an enhancement. Treat spec-fail as their cost, including a workaround they propose.
Sprintlaw (3 June 2026) (Australian colour, not England-and-Wales statute): define defects versus enhancements, and whether fixes sit in the fees. A warranty defect fails a signed criterion; a change request is new want. If the fight is the whole SOW wrapper, that is a different hunt: statement of work review checklist. Stay here for their-cost versus change order. Do: write the test on the card. Don’t: pay for a spec-fail labelled enhancement.
When to treat five days of silence as a deemed-acceptance trap?
Five days of silence deems the deliverable accepted. An inbox miss starts clause 9. Felthouse v Bindley (silence is not acceptance of an offer) does not rewrite a signed SOW. Log five-day silence as fail unless a realistic window, a delivery notice, and a pause when testing is blocked exist.
ReviewMyContract: 15 business days is the sample they treat as reasonable; 5 is not enough for complex deliverables. GetProjects: if the full suite takes six tester-days, a five-day window is a formality. Pinsent on SAM v Hedley: defective software that had never worked properly; Hedley still lost because it missed the rejection machinery. For example, a holiday freeze plus no pause starts the clock. Do: named inbox, ready-for-testing notice, pause when blocked. Don’t: bank on Felthouse.

What does this hunt skip — knowledge-qualified warranties and claims bars?
This hunt is how long they must fix after Acceptance. A knowledge qualifier is whose knowledge. A contractual limitation is when she may bring a claim. Neither is clause 9. Don’t: run those hunts here. Stay on 8 and 9.
If the fight is knowledge qualifiers on representations and warranties, that is a different hunt — see how to review knowledge qualifiers on representations and warranties. If the fight is a bar on bringing a claim — invoice versus knowledge, shorter than six years — that is a different hunt — see how to review a contractual limitation period and late-claims bar. Stay here for how long they must fix after Acceptance. Freeze the packet — the MSA, this SOW, and any acceptance schedule dated today — plus any exhibit — attached warranty or change-order appendix. Open 8 and 9. Do: one sentence to B52; one sentence to the claims bar.
How do you lengthen, carve latent, or walk?
Lengthen the defects window, carve latent and fraud so a hidden spec-fail is still their cost, or walk. Do not sign Friday if thirty days, five-day silence, a change-order latent, and no carve-out remain. Escalate that package. Pause the slot.
Buyer-ask colour, not a statute: 90 days from go-live, not thirty from a silence-Acceptance. Tollen usually gets more than thirty. In practice, walk if the package stays. Escalate that package to counsel — the England-and-Wales solicitor who opens clauses 8 and 9.
Success bar: a one-page log plus one sentence that would pause Friday. Della already has four: 30 days; 5-day silence; change-order latent; no carve-out. Workflow: acceptance clock (not invoice) → latent / fraud carve-out → their-cost vs change order → five-day silence trap → fence B52 / B71 → lengthen / carve latent / walk. Verify 8 and 9 before you sign. Optional: upload the same PDF to document analysis for a first-pass — a machine extract before a human reads every page — then a human still opens 8 and 9 and verifies every High flag — a high-severity extract a named reviewer still opens.
Pause sentence
On Della’s paper: 30 days from Acceptance (vendor floor); five days’ silence (fail); no latent/fraud carve-out; live bug billed as change order.
Hunt
Freeze the packet
MSA + this SOW + acceptance schedule, dated today. Search defects liability / thirty / Acceptance / deemed / five days. Open clauses 8 and 9.
Hunt the start date
Circle “thirty (30) days from Acceptance.” Write Acceptance / go-live / invoice. If silence under clause 8 is Acceptance, the thirty days may already be running.
Hunt the latent / fraud carve-out
After day 30, a hidden spec-fail needs a limb. None here = fail. Do not treat s.5 as a free-fix extension.
Hunt their-cost vs change order
Defect = signed-spec fail. Change order = new want. Della’s live-load bug billed as a paid change order = the play already running.
Hunt deemed acceptance
Circle five (5) days of silence. Redline: ready-for-testing notice, named inbox, window that fits her UAT, pause when blocked.
Lengthen, carve latent, or walk
Ask colour: 90 days from go-live. Carve latent and fraud. Walk if 30 days + five-day silence + change-order latent + no carve-out remain.
Frequently asked questions
Does acceptance kill all claims?▼
How long is a normal defects period?▼
Who pays for a workaround?▼
Does five days of silence count as acceptance?▼
Is this the same as a knowledge-qualified warranty?▼
What to do next
How to Review Knowledge Qualifiers on Representations and Warranties
If the fight is “to the best of Seller’s knowledge” on a warranty, that is a different hunt.
RelatedStatement of Work Review Checklist Before You Sign
The whole SOW wrapper — named MSA, deliverable counts, signed change orders — not this defects clock.
RelatedHow to Review a Notices Clause for Method and Deemed Receipt
How notice is served and when it is deemed received — not five-day silence as deemed Acceptance.
RelatedHuman Verification Checklist for High-Severity Contract Flags
A named reviewer still opens clauses 8 and 9 after first-pass.
Sources
- David Tollen — How long should a warranty last? (updated 10 April 2023)
- ReviewMyContract — Software development agreement guide
- Sprintlaw — Defining acceptance criteria (3 June 2026)
- GetProjects — Acceptance criteria in a software contract
- Pinsent Masons — SAM Business Systems v Hedley
- JCT — Making good with rectification periods
- Gebai — The defects liability period explained (20 July 2026)
- BuildAlliance — What is a defects liability period in construction?
- Fenwick Elliott — Contractual liabilities post completion
- Witan Solicitors — Latent defect periods
- Limitation Act 1980 section 5
Related guides


